Gas may dash Big Oil's Namibian dreams 



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>ANALYSIS-Gas may dash Big Oil's Namibian dreams </title></head><body>

More gas than expected in fields

Geology means oil will cost more to produce

First production may be next decade

Government wants joint gas plan

By Ron Bousso, America Hernandez and Wendell Roelf

PARIS/CAPE TOWN, Nov 7 -International companies and the government of Namibia had high hopes only months ago they could quickly cash in on offshore discoveries and turn the country they saw as the world's last frontier of untapped oil into a prolific producer.

They have since hit a major complication: an unexpectedly high percentage of gas in the fields, meaning they need to install additional infrastructure. That will slow development and may make projects unprofitable, according to executives, politicians and industry sources.

"What we are seeing is that all our discoveries have a very high gas-to-oil ratio," Namibia's Petroleum Commissioner Maggy Shino told an industry conference last month.

Namibian law bans flaring - or burning gas off, releasing CO2 into the atmosphere - meaning companies will have to inject the gas back into the reservoir or process it for consumption, which Shino said was in any case the right thing to do.

"We really want to utilise the gas and generate as much value as possible ... and start then the industry of gas-to-power and petrochemicals, established in Namibia," she said.

After initially hoping for first oil by 2026, Namibia's government is working with operators to agree on a single plan with common infrastructure for the 8.7 trillion cubic feet (tcf) of unexpected gas.

The idea is to revamp a long-stalled project to pipe gas to an onshore gas-fired power plant to supply Namibia, then neighbouring South Africa and the wider region.

Initially designed to handle 1.3 tcf from Namibia's smaller Kudu field, the power plant project and related gas infrastructure would need significant upscaling.

Namibia's government has started talks with Shell SHEL.L, Total TTEF.PA, Galp GALP.LS and Norway's BW Energy BWE.OL, and wants Namibia's national oil company Namcor lead the gas development plan.

For the companies, the problem is the additional work could delay oil production into the 2030s, making it harder to monetise.

Although the industry says oil will be needed for decades to come, the International Energy Agency (IEA) estimates global use will peak before 2030 as the world weans itself off carbon-emitting fossil fuels and as electric vehicle use increases, led by the world's biggest commodities consumer China.

For the major companies that have acquired or are seeking to invest in stakes in development blocks, that is a setback, industry sources told Reuters.

GUYANA DREAM FADES

The oil industry leapt to attention in February 2022 when France's TotalEnergies and London-listed Shell announced major discoveries in Namibia's Orange basin holding a cumulative 5.1 billion barrels of oil.

Investors piled in this April when Portugal's Galp said it found as much as 10 billion barrels in the same area.

Many drew comparisons to Guyana, where discoveries in 2015 led to an oil bonanza that has given the country GDP growth above 20% for the last five years.

But the high gas content, which became apparent over the last year as operators carried out more extensive drilling of reservoirs in Namibia, has since made oil majors cautious.

"We are working on it ... It's a matter of being able to re-inject all this gas in the reservoir at a cost that is acceptable," TotalEnergies CEO Patrick Pouyanne told investors in New York last month.

Injecting gas back into rock under 3,000 metres (9842.52 ft) is already expensive, Pouyanne said. "If we have to have a big gas machine handling 500 million standard cubic feet per day instead of 200 or 300, of course, it changes the dimensions."

Total is struggling to get production costs in Namibia under $20 per barrel - an internal requirement for a final investment decision (FID) on new projects. The company is considering re-negotiating terms with authorities to try to lower costs.

It still hopes to take a FID next year and produce first oil in 2029 based on a plan to reinject all the gas rather than wait for a common solution, said one person familiar with the company's thinking, speaking on condition of anonymity.

The final decision would depend on whether the project would still be profitable enough, another source said.

"Namibia underwhelms," Jefferies analyst Giacomo Romeo summed up in an investor note. Total proposed a smaller-than-expected development of 160,000 barrels per day and did not restate previous hopes for a FID in 2025, Romeo said.

Shell has considered building a floating gas liquefaction unit at the oilfield to produce LNG for export at the block where it made the Graff discovery, according to one source. That would significantly increase development costs and delay oil output start-up.

Shell declined to comment.

Shell CEO Wael Sawan told analysts on Oct. 31 that Namibia's acreage was "very challenging," and that the lower permeability of the rock made extracting oil and gas harder.

"A lot of our focus is on figuring out whether we can find ways to be able to develop commercially investable projects," Sawan added.

Galp, which has put half its Namibian stake up for auction, has postponed the sale pending results of additional exploratory drillings later this year. U.S. major Chevron, as well as Rhino Resources, which is backed by BP and Eni’s ENI.MI joint venture Azule Energy, are also expected to drill in Namibia this year.



Reporting by America Hernandez in Paris, Ron Bousso in London; Editing by Simon Webb and Barbara Lewis

</body></html>

免责声明: XM Group仅提供在线交易平台的执行服务和访问权限,并允许个人查看和/或使用网站或网站所提供的内容,但无意进行任何更改或扩展,也不会更改或扩展其服务和访问权限。所有访问和使用权限,将受下列条款与条例约束:(i) 条款与条例;(ii) 风险提示;以及(iii) 完整免责声明。请注意,网站所提供的所有讯息,仅限一般资讯用途。此外,XM所有在线交易平台的内容并不构成,也不能被用于任何未经授权的金融市场交易邀约和/或邀请。金融市场交易对于您的投资资本含有重大风险。

所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。

本网站上由XM和第三方供应商所提供的所有内容,包括意见、新闻、研究、分析、价格、其他资讯和第三方网站链接,皆保持不变,并作为一般市场评论所提供,而非投资性建议。所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为适用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。请确保您已阅读并完全理解,XM非独立投资研究提示和风险提示相关资讯,更多详情请点击 这里

风险提示: 您的资金存在风险。杠杆商品并不适合所有客户。请详细阅读我们的风险声明